Coulter Timeline

2025 DatesEventNotes
January 14 – February 27Call for Preliminary ProposalsApplicants strongly encouraged to meet with the Coulter Program

Director prior to submitting a proposal. 
February 28Preliminary Proposal due date5:00 pm Feb 28 due date
TBD (April 4 – 11) Target Date April 4Initial Review MeetingUp to 10 teams will be invited to the Initial Review Meeting

20-minute pitch and Q&A with the Coulter Oversight Committee (OC).
April – mid-JuneProposal Support Program (PSP)Up to 8 teams will be selected for Project Selection meeting

Clinical and commercial opportunity assessment market research will be conducted to support proposal refinement

PSP deliverables include:
1. Target product profile development, budget and milestone refinement suggestions
2. Final proposal and Selection Meeting pitch presentation
Mid-JuneProject Selection Meeting20-minute pitch and Q&A with the OC Funding awarded up to 8 teams
JulyFunding beginsOne-year funding from July 2025 – June 2026